Building with Sekisui our journey started last year upon buying a old house in our area to knock down and rebuild on 4th July2013 then we went on the journey to find a builder for our land and a house that would fit on our 15.24 mtr x 48 mtr block, being that width was always going to be a issue.We had been looking prior to buying and always love the Eden Brae and Metricon, the problem was that every time we found a design we liked they said we had to make it narrower, or go down to the size below and we didn't like that, we then stumbled upon Sekisui , the sales consultants were great and weren't at all pushy, they had time to talk and listened to what we wanted,they suggested the new range the arise collection and said that we should look maybe at the acacia, we fell for it straight away, it had every thing we wanted, principle suite at the rear of the house, a room down stairs for my 17 year old daughter with ensuite and walkin robe, alfresco and a big room for my son and his mates upstairs , every one had there own space. We have made a ton of changes to give it our own personal touch. So here is the dates and our journey
4/7/13 purchase a kdr house
13/7/13 dep $2000 Sekisui to go ahead with plans and drawings
18/8/13 site analysis report
1/9/13 initial tender and pricing
18/9/13 new tender and pricing due to new offers
30/10/13 $ 3000 dep for go ahead
8/11/13 customer service person appointed
9/11/13 1st colour selection
23/11/13 2nd colour selection
2/12/13 plans to water board for stamping
9/12/13 plans to mine subsidence
13/12/13 temporary fencing by us put up for demolishen ready
17/12/13 electricity disconnected and builders pole erected
22/1/14 plans sent back from council for geo tech stamping

4/3/14 plans approved for demolishen and building

17/3/14 construction certificate approval

24/3/14 new colour selection and check
11/4/14 clearance certificate from demolishers arrived
1/5/14 new pricing final
28/5/14 peg out survey received so we can do retaining wall and excavation for pads for building .
20/6/14 on site customer service person appointed
24/6/14 bore holes done and concrete in holes yay only 40 lm and they allowed for 60 lm so we may get a credit.


That's all for now, will try and post some pics
Hope you all enjoy this thread. Cheers :D

Week of 6/7/14 frame delivered , concretors finished, 7/714 started frame 

24/7/14 second story up, 25/7/14 bricks delivered and brickies have started to set out .
As of 8/8/14 they are going great guns, roof on, bricks finished, guttering and faciers, and eaves should be completed as of 9/9/14 and starting of the top weatherboard.

 
 
 
 
 
 
 
 
 
 
 
 

Exciting Signs and Porty Loo

After Bore Holes and filled with Concrete Tue 24th June 2014
Second Level


Origonal Plans